estimated Schedule
Below is a timeline of the development of the proposed Preserve at Thousand Oaks planning unit development. This is proposed to be constructed in six, total phases. The timeline is at the discretion of the developer and is subject to change, based on the market/interest rates.
| # of Lots | Begin Development | Complete Development | Begin Home Construction | Home Closings Begin |
Phase 1 | 121 | Oct 2022 | Oct 2023 | Nov 2023 | Mar 2024 |
Phase 1A | 30 | Oct 2022 | Oct 2023 | Nov 2023 | Mar 2024 |
Phase 2 | 215 | Jan 2024 | Jan 2025 | Feb 2025 | Jun 2025 |
Phase 3 | 310 | Jan 2026 | Jan 2027 | Feb 2027 | Jun 2027 |
Phase 4 | 269 | Jan 2028 | Jan 2029 | Feb 2029 | Jun 2029 |
Phase 5 | 13 | TBD | TBD | TBD | TBD |
Phase 6 | 2 | TBD | TBD | TBD | TBD |
As of 07/15/22
Please view the proposed concept plan, PUD standards, and PowerPoint presentation that were presented to City Council on June 28, 2022.